The City Council is being asked to approve a construction contract with J3 Company, LLC to rebuild Culebra Road between IH-10 and Callaghan Road. The contract has a maximum value of $13,737,258 and is part of the 2022 Bond Program. The ordinance also allows an incentive payment of up to 10% of certain project funds if the contractor finishes early.
The contract is capped at $13,737,258. Of that, San Antonio Water System (SAWS) will reimburse the city $1,789,374 and CPS Energy will reimburse $798,575.73 for their related utility work. Funding comes from the 2022 Bond Program and the Tree Preservation and Mitigation Fund in the FY 2026 budget. An additional incentive of up to 10% may be paid from the project's contingency, incentive allowance, or other available project funds for early completion.
The item is presented by Assistant City Manager John Peterek and Capital Delivery Director Michael Shannon. J3 Company, LLC would receive the contract; SAWS and CPS Energy share in the cost for their utility work; and people who live, work, or travel along Culebra Road between IH-10 and Callaghan Road would be affected by the construction.
The agenda identifies this as a 2022 Bond project, meaning it was included in the bond package approved by voters in 2022. No other prior actions are described.
Show the original agenda text
Ordinance approving a construction contract with J3 Company, LLC for the Culebra Road (IH-10 to Callaghan Road), a 2022 Bond project, in an amount not to exceed $13,737,258 of which $1,789,374 will be reimbursed by San Antonio Water System (SAWS), and $798,575.73 will be reimbursed by CPS Energy; and authorizing an incentive payment up to 10% from the project‘s contingency, incentive allowance, or other available project funds for early completion. Funding is from the 2022 Bond Program and the Tree Preservation and Mitigation Fund FY 2026 Adopted Budget and is included in the FY 2026 Capital Budget.